Resources
Practical checklists you can use this week.
Free working tools from our approach. Open one, copy it, and use it on your next update.
Long-lead equipment readiness checklistProcurement · 8 checks
- Required-on-site date derived from the schedule, not the vendor quote.
- Purchase order date, approval drawing return and release-for-fabrication dates logged.
- Vendor data requirements (IFA/IFD drawings, test procedures) tracked with owners.
- Factory acceptance test date confirmed and witness attendance planned.
- Shipping method, route survey, rigging and laydown confirmed.
- Payment milestones mapped against your billing and funding dates.
- Float to required-on-site date reported every update.
- Fallback identified: alternate vendor, surplus unit or resequenced work.
Month-end controls and finance calendarReporting · 6 steps
- Agree one data date for schedule, cost and progress.
- Collect field and engineering progress against rules of credit.
- Update the schedule; review critical path and float changes.
- Reconcile actuals and open commitments with accounting.
- Update the forecast at completion and explain variances.
- Issue the reporting pack before finance closes the month.
Schedule health check: ten questionsScheduling · 10 questions
- Does every activity have at least one predecessor and one successor?
- Are hard constraints few, justified and documented?
- Are lags and leads limited and explained?
- Is the critical path continuous from data date to completion?
- Are durations realistic for the work and calendar?
- Are actual dates all before the data date?
- Is high total float explained, not left open-ended?
- Are procurement and vendor data activities linked to construction?
- Do calendars reflect real shifts, holidays and outages?
- Does the WBS map to cost codes and reporting lines?
Surplus equipment: what to documentEquipment · 7 items
- Nameplate photos and manufacturer model numbers.
- Ratings: voltage, current, kVA or kW, interrupting rating, frequency.
- Standards and certifications (for example UL, ANSI, IEEE).
- Condition: new and crated, installed, or used, with storage history.
- Test reports, drawings, manuals and warranty status.
- Location, rigging needs and earliest available date.
- Seller constraints: confidentiality, pricing expectations, timing.